Bush Beast Construction

The Bush Beast was a “Double out & back figure 8” configuration, a direct clone of Paramount Canada’s Wonderland’s Wild Beast built in 1981.

Bush Beast Construction (16)
Paramount Canada’s Wonderland’s Wild Beast

The Bush Beast was prefabricated on site and assembled like a giant construction kit out of 450,000 board feet of imported Southern Yellow Pine and held together with over 30,000 steel bolts and 9,072 Kg of nails.

The Bush Beast’s construction started on the 1st of April 1985 and was completed on the 5th of November 1985 at a cost of $2.7 million.

The Bush Beast was built to last 40 years.

Bush Beast Construction Time Line

30th of April 1985

The first component of the lift hill goes into place.

You can see what is meant by “assembled like a giant construction kit”, when you look at the pictures above and below that where taken on the same day only a few hours apart.

The first component of the main 25 meter drop is built, at the same time the lift hill was completed.

Bush Beast Construction (15)
Bush Beast Construction (14)

14th of May 1985

Bush Beast Construction (photo 1)

30th of May 1985

Bush Beast Construction - construction, May 1985

17th of June 1985

Bush Beast Construction (photo 2)

1st of August 1985

Bush Beast Construction (photo 3)
Bush Beast Construction (photo 4)

Construction was completed on the 5th of November 1985.

Bush Beast Construction (photo 5)
Bush Beast Construction (photo 6)

Construction workers signed their name in 2 locations on the Bush Beast.

The first location was on the side of the floor just underneath the original top landing for the exit ramp, which was later converted into the Control Booth when the Bush Beast went to 1 person operation. This was dated 4/11/85 and was accompanied with the name Mark Dearing. You could notice it as you walked down under this landing and looked back.

The second location was on the side of a horizontal brace which supported the maintenance platform that serviced brakes 1 to 4 under the station, this was dated 5/11/85.

Tuesday the 5th of November 1985 was the last day of construction. This gave a little over 4 weeks to commission the ride and add final touches to the theming of the Bush Beast before the park opened.
 

Bush Beast used fin type breaking pioneered by taft, Bush Beast was computerized, the computer aka PC (programmable controller) controlled everything on the ride, and would shut down the ride if there was any fault.

The Bush Beast was prefabricated on site and assembled like a giant construction kit out of 450,000 board feet of imported Southern Yellow Pine and held together with over 30,000 steel bolts and 9,072 Kg of nails.

The Bush Beast’s construction started on the 1st of April 1985 and was completed on the 5th of November 1985 at a cost of $2.7 million.

You can see what is meant by “assembled like a giant construction kit”, when you look at the pictures above and below that were taken on the same day only a few hours apart.

Bush Beast used fin type braking pioneered by taft, Bush Beast was computerised, the computer aka PC (programmable controller) controlled everything on the ride, and would shut down the ride if there was any fault.